7/22 dirt starts to fly

8/5 pad in place

9/3 utility lines going in

9/5 utility lines covered

9/17 the footers and slab are framed

9/30 Ready to pour slab

10/1 Pouring the slab

10/2 Slab is in.

10/2 Lumber arrives.

10/3 Framing begins

10/9 Framing continues

10/10 Trusses are up!

10-18 Sheathing

10-29 waterproof barrier begun

11-5 Foam insulation installation

11/16 Stucco underway

11/19 Color going on

11/22 Front doors installed

11/22 drywall complete

11/22 Finish stucco & paint

12/5 paving complete

12/9 Parking lot striping